Experience

  • June 2013 - Present

    Project Manager, Hammerfest Industriservice AS

    • Buzău, Romania
    • Full time
    • Work domain - Engineering: Energy / Extractive Industries,Industries / Production / Manufacturing

    Project Manager

  • December 2012 - May 2013

    QA/QC Engineer, SC TECNOSERVICE Bucuresti SA

    • Buzău, Romania
    • Full time
    • Work domain - It Telecom: Engineering

    -Drafting technical documentation of products (pressure vessels, loops and 
    ducts for flue gas treatment)
    -Quality control of fabrication
    -Drafting of NDT Plan
    -Welders certification and WPQR’s coordination
    -Hydraulic and final test inspection of pressure vessels
    -Painting inspection of products
    -Materials inspection
    

  • January 2012 - April 2012

    Precommissioning coordinator: , SC TMUCB SA

    • Buzău, Romania
    • Full time
    • Work domain - Engineering: Industries / Production / Manufacturing

    Company: S.C. TMUCB S.A. Bucharest, Romania (Joint Venture EAMT)
    EPCM Contractor: Tecnicas Reunidas
    Employer: Hellenic Petroleum
    	
    Job description: 
    -Inspection and assessment of the Piping Systems to find the proper modality 
    for cleaning by flushing or/ and blowing. 
    -Coordination with piping superintendent in preparing the piping systems 
    for flushing or/ and blowing.
    -Piping inspection before and after reinstatement.
    -Planning, Execution, Control and Supervision of all activities like Test pack 
    and Test equipment preparation.
    -Planning, Execution, Control and Supervision of all activities like Pneumatic 
    testing, Hydro testing, Watering, Dewatering, pressurizing, Depressurizing of 
    pipeline.
    -Monitor work permit issuances and check strict implementation of all safety 
    requirements during testing & pre-commissioning works.
    -Review of Hydrotest Package and check the limit of test pack.
    -Confirm all valves are set to the pre test position shown in the system P&ID limits.
    -Isolation Hand Valves have been set in positions specified by the checklist prior 
    to the test.
    -Verify that all instruments have been installed, tested and connected.
    -All necessary blinds have been installed as per isolation plan. Confirm all 
    spectacle blinds and temporary commissioning spades are in the pre test 
    position shown in the system P&ID limits.
    -Ensure direction and location of check valves do not interfere with pressuring 
    or depressuring the system.
    -Do line walk and final inspection in preparation for testing.
    

  • August 2011 - January 2012

    Erection Material Coordinator, SC TMUCB SA

    • Buzău, Romania
    • Full time
    • Work domain - Engineering: Energy / Extractive Industries

    Company: S.C. TMUCB S.A. Bucharest, Romania (Joint Venture EAMT)
    EPCM Contractor: Tecnicas Reunidas
    Employer: Hellenic Petroleum
    	
    Job description:
    -Requisitions erection materials and establishes sequential delivery dates to site, 
    according to job order priorities and material availability.
    -Examines material delivered to site to verify conformance to specifications.
    -Compiles and maintains manual and computerized records, such as material 
    inventory, in-process production reports, and status and location of materials.
    -Coordinate the transport of materials from warehouse to site.
    	

  • June 2010 - August 2011

    Workshop piping prefabrication supervisor, SC TMUCB SA

    • Buzău, Romania
    • Full time
    • Work domain - Engineering: Industries / Production / Manufacturing

    Company: S.C. TMUCB S.A. Bucharest, Romania (Joint Venture EAMT)
    EPCM Contractor: Tecnicas Reunidas
    Employer: Hellenic Petroleum
    	
    Job description:
    -To supervise shop fabrication of piping.
    -Check and provide prefabrication materials and delegate work to employees.
    -Perform Isometric checking to ensure the correct material use for construction.
    -Technical coordination with staff.
    -Execution and monitoring of the works.
    -Coordinate the transport of prefabricated spools from workshop to site.

  • August 2009 - June 2010

    Welding Engineer, SC ENERGOMONTAJ SA

    • Buzău, Romania
    • Full time
    • Work domain - It Telecom: Engineering

    Company: S.C. Energomontaj S.A., Bucharest, Romania
    	
    Job description:
    -To coordinate the welding works of the company
    -To approve welding project and technologies
    -To approve the filler material list and also welding and thermal treatment equipment works
    -To provide the required trained and approved personnel for the welding works
    -To issue WPS and WPQR for welding works of the company
    	

Education

  • 2004 - 2009

    Bachelor's degree, University "Politehnica" of Bucharest

    • București, Romania

Skills

Driving license
  • B

Foreign languages

English
Advanced
French
Intermediate
Spanish
Intermediate
Romanian
Native